Flow was awarded the project of turnkey design and installation of piped services of a large extension to an egg hatchery in New Plymouth in 2015. This included a high efficiency boiler plant, cooling water piping, compressed air, wash-down water. Due to the nature of the project a lot of planning and prefabrication occurred so the services were ready to complete once the hatchery equipment arrived leaving only a few weeks to connect, test and successfully commission. All shutdowns had to be coordinated and timed to minimise disruption to the old plant that was running at 100% capacity 24/7

0m
Of Pipe Work Installed
0+
Man Hours
0
Water Pumps
0Kw
Boiler Plant
0mil +
Egg’s in incubation kept at precise humidity and temperature 24/7